Please assist to solve,

Ravi and Sam painted a house together. Sam felt sick and rested for 6 days and Ravi took a day off. If they had to do the job alone, Sam would take 10 days and Ravi would take 15 days. How long did the two men take to complete the painting of the house

Thanks

Forum Chatty
Chatty

Registered: 12/31/06
Posts: 53

Profile Email    
   
By: echeewh (offline)  Saturday, August 23 2014 @ 09:32 PM CDT  
echeewh

Hey <sundarshoba>

Following is my worked solution:

<Work Rate - fraction of house painted alone per day>
S: (1/10)
R: (1/15)
R + S: (1/10) + (1/15) = (5/30) = (1/6)

R painted alone for 6 days:
(6/15) = (2/5)

S painted alone for 1 day:
(1/10)

Fraction of house painted together (R + S):
1 - (2/5) - (1/10) = (5/10) = (1/2)

Number of days to complete by (R + S):
(1/2) รท (1/6) = 3

Total days taken to paint house:
6 + 1 + 3 = 10 days

========

Trust this helps

Do let me know again if this is different from your <Answerkey> or if there's further clarification.

Cheers,
Edward

Forum Active Member
Active Member

Registered: 04/21/11
Posts: 627

Profile Email    
   


 All times are CDT. The time is now 06:38 am.
Normal Topic Normal Topic
Locked Topic Locked Topic
Sticky Topic Sticky Topic
New Post New Post
Sticky Topic w/ New Post Sticky Topic w/ New Post
Locked Topic w/ New Post Locked Topic w/ New Post
View Anonymous Posts 
Able to Post 
HTML Allowed 
Censored Content